3g Group

Claims Management & Advisory

In UAE construction, the difference between a recovered claim and a failed one is almost always notice discipline, quantum rigour, and expert preparation. 3EG delivers all three — with in-house QS and planning under one roof.

Types of Claims We Handle

Extension of Time (EOT) Claims
EOT claims are the most common — and most frequently failed — claims in UAE construction. Failure to serve a notice within the required timeframe stipulated in the Contract upon becoming aware of a delaying event constitutes a condition precedent, the breach of which may bar the entire claim regardless of its merits. 3EG’s claims management service begins with notice discipline — ensuring entitlements are preserved from the moment a delaying event occurs.
An EOT without associated prolongation cost recovery is only half the claim. Once entitlement to additional time is established, the associated time-related costs — site overheads, supervision, equipment, and finance charges during the extended period — must be properly quantified and substantiated.
Disruption claims — addressing the loss of productivity caused by employer-risk events — are among the most technically complex claims in construction law. 3EG applies internationally recognised methodologies to quantify disruption loss, supported by contemporaneous labour and programme records.
3EG prepares comprehensive, substantiated final accounts and provides experienced negotiators to achieve the best possible settlement — or, where necessary, to present the case effectively in dispute resolution proceedings.

The 28-Day Rule — What Every UAE Contractor Must Know

Under FIDIC Sub-Clause 20.1 (1999 edition) and Sub-Clause 20.2 (2017 edition), a contractor seeking an Extension of Time or additional payment must give notice to the Engineer within 28 days of becoming aware of the event or circumstance. This notice requirement is a condition precedent — fail it, and the entire claim can be barred regardless of its merits. UAE and DIFC courts have confirmed that the 28-day clock runs from when the contractor “was aware, or should have been aware” of an event that could give rise to a claim — even if no actual delay has yet materialised. Contractors must issue notices for prospective delays, not just delays that have already occurred.

You’ll Know What

We are Transparent Like that. No Gimmicks.